Project Progress

Follow the construction journey for No. 1 Church St with our regular updates. We provide monthly summaries of the progress on site, to ensure future residents, the local community and any interested parties are up to date with what’s happening at this iconic Dubbo building.

Click through the timeline below to see the journey!

January 2026
Progress continues through December into January, despite the Christmas break

Progress has continued through December and into January, despite the Christmas break, with the pool now installed, ground floor glazing progressing across the lobby, light well and commercial areas, and waterproofing and plumbing underway in preparation for ceilings and wall fit-off. Works are also advancing on balcony privacy screens and window blades, rooftop solar and mechanical systems, remaining apartment cabinetry, and the final stages of tiling, plastering, painting and floor coverings as apartments are completed.

November 2025
Levels 11 and 12 are now fully framed

Steady progress continues at No. 1 Church Street as we move into November. Rooftop services ductwork is being installed, Levels 11 and 12 are now fully framed, and plasterboard is underway on Level 11. Kitchens are starting on Level 9, while tiling has reached Level 7 with carpet and vinyl due to begin next week.

October 2025
Joinery installs progressing on level 7

Over the past few weeks, joinery installs have been progressing on Level 7, while waterproofing preparation is underway on Level 8. The roof is now fully waterproofed, priming has reached Level 7, and the majority of windows are in place. External cladding is nearing completion, with framing continuing to rise on Level 12.

September 2025
Facade carpark screens are now being fitted

The facade carpark screens are now being fitted, with steel framing installed and ready for the exterior screens to follow - bringing the building’s architectural design a step closer to completion. Internally, fit-out works are progressing steadily with partition walls, plasterboard, joinery, and other trades well underway. All three lifts are now installed, and electrical infrastructure connections are advancing, with final completion by the authority expected in the coming weeks.

Over the next few months, the site will be busy completing the remaining facade works, allowing external landscaping and surrounding areas to be finalised.

August 2025
Watertight testing

Every window is being tested to meet rigorous standards for wind and water resistance – a crucial step before occupation certification. On taller buildings, wind pressure can push water upward, so each unit must pass simulated extreme weather tests. It’s one of the final quality control steps before full enclosure

June 2025
Fit-out advances across multiple levels

Progress continues throughout the building as fit-out advances across multiple levels.

On Level 1, plasterboard installation is underway. Level 2 has seen services rough-in completed, with gyprock, tiling in the new display bathroom, and balcony pavers now in progress.

Windows and sliding doors are now fitted across Levels 1–8. Steel stud framing is progressing from Levels 4–8, while services rough-in continues on Levels 3 and 4.

May 2025
Internal fit-out progressing

Fit-out is progressing well across Levels 1 to 4, with all internal dividing walls now installed. Stud and track framing is complete, and services have been roughed in throughout these levels. Work will continue with gyprock sheeting, cabinetry installation, tiling, and painting in apartments across these floors.

Window installation will advance up the building, with both balcony and non-balcony windows being fitted beyond Level 6. Externally, painting of balconies and precast panels is also underway and will continue over the coming months.

Late March 2025
tree top out
Top out

Late March saw the celebration of the topping out of the build - the moment when the final structural element is placed at the top, marking the transition to the fit-out phase. In Australia, this tradition signifies a safe and incident free build, while in Scandinavian history, a pine tree was hoisted to the top of a framed building to signal that the timber had dried and was ready to be enclosed.

March 2025
Internal fit-out underway

Internal fit-out moving ahead, with plumbing stackwork and electrical trades being installed through the upper floors. Level 1 fire wall installation underway, while the final precast panels are being put in place.

Roof slab pour, scheduled for 25 March - bringing us closer to topping out the structure. Window installation and wall framing have kicked off, giving a clearer picture of the building’s final form.

February 2025
Wall construction and beginning of balustrade handrail installation

Level 9-11 of the apartments formed and poured.

Wall construction on Bligh Street, Church Street, and the Ground Level commenced with services installation—including electrical, fire sprinklers, and mechanical systems—underway.

Installation of the balustrade handrail has begun, bringing another key design element to life.

December 2025
Level 7 of the apartments poured

Level 7 poured and precast panels successfully installed.

Lighting and sprinkler fit-outs in the car park levels underway.

November 2025
Level 5 of the apartments poured

Level 5 of the apartments poured - that's another 250 cubic metres of concrete pumped and placed.

The lower levels of the building are stripped of their form work in readiness for installation of services and the divisional wall construction.

October 2024
working carrying a wooden beam
Form work for level 7 and precast panels have been installed

Levels are going up quickly now, with level 6 now poured (that's level 3 of apartments). Form workers have been busy establishing the form work for level 7 and precast panels have been installed and post tension is also complete. The scaffolding is being stripped from the lower levels, revealing the lower parts of the concrete structure.

The building is really beginning to take shape!

September 2024
view of the no1 churchst construction from church st
Safety screens installed

Safety screens installed. These finishing screens can be moved up the building as required. The screen set-up facilitates the parallel works of both structure and finishing works. The screens ‘climb’ the building as the works progress, allowing the entire construction process to be facilitated behind the full protection of the screens, increasing general site safety and efficiency.

August 2024
concrete slab being poured
Concrete pouring for each level occurring almost weekly

The construction at No. 1 Church Street is in full swing, with the concrete pouring for each level occurring almost weekly. 

The installation of precast panels and columns for level 2 to take place in early September, as well as the form work and installation of steel reinforcement for level 3.

Other work taking place in the lower levels includes installation of stair access and preparation works for infrastructure to be installed in the coming weeks.

June 2024
carpark ramp concrete pour
Installation of the formwork for the commercial level and mezzanine carpark

Installation of the formwork for the commercial level and mezzanine carpark - approximately 2000m² - commenced in early June, followed by the pouring of concrete in this area. All major trades have been on-site, installing services.

Late May 2024
Tower crane installed on-site

Tower crane installed and the carpark concreting 90% complete. Precast walls and columns were installed, along with the final concrete pouring for the fire stairs and waste room.

May 2024
Precast vertical columns and walls to ground level being set in place

In May, we reached a landmark moment at No. 1 Church Street, with the precast vertical columns and walls to ground level being set in place.

This was a critical stage of construction, as we moved on from groundworks and saw the actual structure of the project begin to take shape.

April 2024
First panel lifts

In mid-April we passed a big milestone for the project with the first panel lifts completed After some delays due to weather, this was an exciting moment for all on site - seeing some height after months of ground works!

2024
February 2024
pour of raft slab
In ground works completed

The final pour of the raft slab commenced (with Council approval) at 2am on Wednesday 28 March to complete all in ground works. A total of 80 truck loads of Redimix Concrete from Regional Quarries was used in the pour. According to the Redimix team, this was the largest single pour undertaken by Redimix Concrete in Dubbo.

2023
December 2023
groundworks
All 121 piles completed

The crew have been busy working on the site to ensure all 121 piles have now been completed and tested.

Work has now commenced on the civil in-ground storm water, retaining walls and drainage and a section of the raft slab to the eastern boundary.